Building renovation contractor Balham London SW12

Internal building refurbishment October 2012

The old school building internal refurbishment and renovation is going very well. Internal renovations and improvements include: a new heating system, re-wiring, plumbing and decorating.

Plumbing and electrics: Most of the re-wiring and plumbing is now complete.

Boiler room: Two modern ultra-efficient condensing boilers have been installed in the basement boiler room.

Decor and flooring: Plastering, dry lining and decorating continues with floors being cleaned up and prepared for carpet or sanding and vanishing.

Building refurbishment and renovation schedule

We estimate the project should take approximately six weeks to complete from the beginning of November 2012.

Work continues on site !

Building refurbishment December 2012

The project is close to completion with manly cosmetic finishes remaining. Some final decorating, wooden floor polishing and cleaning up the whole interior.

In the basement, to rectify an age old problem from the past, the plant room is being tanked to protect the brand new electrical and heating systems and services from damp / water damage.

Public liability insurance

Nationcare Windows Ltd is fully insured to carry out public works and adheres to health and safety guidelines.

We are an approved local government double glazing contractor specialist in large scale double glazing developments.

Key property double glazing development projects include block of flats and apartments, complete housing estates with hundreds of houses, school and hospital buildings.






  
    
 

smallbranch website design

Associated links: A3fixings.co.uk